Metrics was appointed to deliver the façade design for LON 4, a high-tech data centre in Slough. The project demanded a highly coordinated and technically disciplined approach, with the design developed in accordance with stringent client-led processes and exacting project requirements. Working within a federated Revit model environment enabled the façade package to be coordinated alongside the wider building design, helping the team identify interfaces, manage information efficiently and maintain design clarity throughout the detailed design stage.

Design Scope

Our Stage 5 façade design scope encompassed the complete curtain wall façade, taking the system from detailed design through to a fully coordinated and buildable solution. A key consideration was the significant level of anticipated building movement, which required high-deflection detailing to be carefully integrated throughout the façade. The glazing was also engineered to accommodate the required wind and barrier loadings, ensuring that each component responded effectively to the project’s structural and performance demands while retaining the intended architectural appearance.

Our Approach

Close technical collaboration was fundamental to the successful development of the façade. We worked directly with Kawneer’s technical department to develop robust high-deflection details and resolve the integration of the feature deep aluminium nosing cap, including the fixing and restraint strategy required for reliable performance. The building geometry introduced further complexity at the entrances, where cantilevered transoms created demanding structural and detailing conditions. Through focused coordination, careful analysis and iterative design development, we pushed the curtain wall system to its practical limits while maintaining a clear, coordinated and fabrication-ready solution. The result was a technically rigorous façade package shaped around the specific movement, loading and geometric challenges of this advanced data-centre development.